Multiple Choice
A project has three possible paths from start to finish. Path A-B-C is 15 hours; path A-C-D is 10 hours, and path A-C-E is 20 hours. Which one of the following statements is true?
A) The expected duration of this project is 10 hours.
B) The expected duration of this project is 15 + 10 + 20 = 45 hours.
C) Path A-C-E is the critical path.
D) Path A-B-C has the most slack.