Given that activity B has the following times, which of the following statements is true about activity B?
Earliest start time = 9 days; latest start time = 17 days; earliest finish time = 15 days; latest finish time = 23 days
A) Activity B has a slack time of 8 days.
B) Activity B is a critical activity.
C) Activity B takes 6 days to complete.
D) Activity B takes 23 days to complete.