Solved

Given That Activity B Has the Following Times, Which of the Following

Question 18

Multiple Choice

Given that activity B has the following times, which of the following statements is true about activity B?
Earliest start time = 9 days; latest start time = 17 days; earliest finish time = 15 days; latest finish time = 23 days


A) Activity B has a slack time of 8 days.
B) Activity B is a critical activity.
C) Activity B takes 6 days to complete.
D) Activity B takes 23 days to complete.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions