Multiple Choice
A contingency amount can be (circle one) :
A) applied to individual activities or work packages
B) applied to the project as a whole
C) continually increased to cover cost escalation
D) all of the above
E) a and b only.
Correct Answer:

Verified
Correct Answer:
Verified