Multiple Choice
Which method provides the least accuracy when estimating total project cost (circle on) :
A) expert opinion
B) analogy
C) parametric
D) cost engineering
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: Which of the following statements are true
Q2: The project planning and estimating process (circle
Q3: Statement: The majority of a system's life
Q4: If the actual cost turns to be
Q6: Statement: A time-phased budget shows project costs
Q7: Statement: The project cost estimate is derived
Q8: A contingency amount can be (circle one):<br>A)
Q9: The major problem with using traditional budgets
Q10: Statement: The feasible budget region is developed
Q11: Statement: Life cycle costs are the same