Which One the Following Is True

Question 4

Multiple Choice

Which one the following is true:


A) the WBS is the basis for project schedules, budgets, and controls.
B) work packages are the basis for project schedules, budgets, and control.
C) both a and b
D) project schedules are the basis for work definition.

Correct Answer:

verifed

Verified