Multiple Choice
For the next three questions, choose letters of the terms in the following list that best fit the questions.
Where (what section or method) in the project master plan are the following questions addressed (Note, some of these terms might also have applied to the above questions; these can be used again.) .
-What is the project all about; what does the project involve?
A) risk plan
B) change control plan
C) responsibility matrix
D) SOW/scope/requirements
E) user needs
F) required contents of proposal
G) qualifications/experience of core team
H) contingency plan
I) project proposal
J) feasibility study
K) project schedule
L) proposal deadline
M) documentation plan
N) WBS/work packages
O) project budget
P) RFP
Q) work review/testing plan
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Procurement management can include which if the
Q3: Which of the following are essential elements
Q4: Which one the following is true:<br>A) the
Q5: Statement: Procurement management refers to the management
Q6: About project schedules, which one is true:<br>A)
Q7: Statement: The statement of work is a
Q8: For the next three questions, choose letters
Q9: Statement: Portions of or even entire work
Q10: For the next three questions, choose letters
Q11: The project SOW includes (circle all that