Multiple Choice
The local representative (circle all that apply)
A) serves as representative or liaison between the project manager and the customer
B) arranges for services in the host country
C) translates business requirements into technical requirements
D) assists in locating local contractors
E) stands in for the project manager at project review meetings
Correct Answer:

Verified
Correct Answer:
Verified