Integration in Projects Involves (Circle All That Apply)

Question 11

Multiple Choice

Integration in projects involves (circle all that apply) :


A) integrating the functional areas of the organization to achieve project goals
B) integrating the phases of the project so that issues concerning later phases are considered in decisions made in early phases
C) treating the functional areas as autonomous units to minimize extraneous influence
D) managing the phases of the project as a series of completely independent subprojects.