Multiple Choice
A heavyweight development team (circle all that apply) :
A) is larger and has more members than most other teams
B) has a project manager who has strong influence and organizational clout
C) controls the resources it needs to get the job done
D) is an example of one kind of pure-project organization
Correct Answer:

Verified
Correct Answer:
Verified