Multiple Choice
The EV represents, at a given time:
A) the amount budgeted for project work as of that time
B) how much work has actually been done and the amount originally budgeted for that work
C) actual expenditures according to time cards and invoices
D) how much it will cost, according to the budget, to complete the project
Correct Answer:

Verified
Correct Answer:
Verified