Multiple Choice
Technical Performance Measurement (TPM) provides (circle all that apply) :
A) an estimate of performance as of a given date
B) a way of determining which performance measures are the most reliable
C) a forecast of ultimate performance given the current rate of development
D) a way for managers to make systematic tradeoff decisions concerning the performance of subsystems and components