Multiple Choice
Ways to control the adverse impact of changes in a project include (circle all that apply) :
A) make sure that original plans and schedules are agreed to by everyone involved.
B) make sure all work exceeds specifications.
C) make many small changes on a continuous basis instead of a few big ones.
D) require that all changes be documented, reviewed, and approved.
E) put a freeze on changes as soon as the system is delivered to the customer.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Statement: A single-value estimate of the completion
Q2: Statement: Project control primarily involves monitoring performance,
Q3: Which of the following are true about
Q5: Match the following formulas with their appropriate
Q6: Statement: The number of changes made during
Q7: To implement a time buffer (circle one):<br>A)
Q8: Among important ways to assess the status
Q9: How or where is work progress measured
Q10: Match the following formulas with their appropriate
Q11: Use the following information to perform an