Essay
Use the following information to perform an earned value analysis.
Summary analysis, as of "Status Date"
a. Complete the PV column.
b. Complete the EV column.
c. What is the value of the work remaining on the project?
d. What is the CPI as of the status date?
e. Given the value of the work remaining and the CPI, what is the estimated cost
to complete the project?
f. Given the actual cost as of the status date and estimated cost to complete, what is the
estimated cost at completion?
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Statement: The number of changes made during
Q7: To implement a time buffer (circle one):<br>A)
Q8: Among important ways to assess the status
Q9: How or where is work progress measured
Q10: Match the following formulas with their appropriate
Q12: Statement: To reduce confusion and increase the
Q13: About the project control process (circle all
Q14: Suppose a project was originally estimated to
Q15: Statement: By monitoring performance indexes and variances
Q16: Statement: Quality control in projects begins with