Essay
The following chart to answer questions (a) through (e). Suppose the project is currently at the end of month 4.
a) When was the project originally scheduled for completion?
(b) What was the original budgeted cost of the project?
(c) As of month 4, how far (in months) is the project behind schedule in terms of the value of work completed? Show on the chart how this is determined.
(d) As of month 4, what is the forecast cost to complete the project, and the forecast cost at completion?
(e) As of month 4, what is the revised completion date for the project? Indicate this and the forecast cost at completion on the chart.
Correct Answer:

Verified
Correct Answer:
Verified
Q31: Statement: The tendency for a project to
Q32: Activity X has four immediate predecessors, three
Q33: Match the following formulas with their appropriate
Q34: Statement: Configuration management refers largely to the
Q35: Statement: The purpose of establishing variance limits
Q37: Statement: External project control refers to the
Q38: Statement: There is little difference between project
Q39: Match the following formulas with their appropriate
Q40: Statement: Earned value is expressed as the
Q41: Statement: The primary purpose of formal reviews