Multiple Choice
Activity X has four immediate predecessors, three of which finish before their late finish date, one that finishes after its late finish date. What effect will this have on Actiivity X (circle one) :
A) it will be delayed
B) it will be delayed only if the late predecessor is on the critical path
C) it will be able to start early if any of the early predecessors are on the critical path
D) none of these
Correct Answer:

Verified
Correct Answer:
Verified
Q27: In controlling projects, data on actual project
Q28: Work progress should be reviewed (circle all
Q29: Issue management: circle all statements below that
Q30: Use the project below.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TBR1472/.jpg" alt="Use
Q31: Statement: The tendency for a project to
Q33: Match the following formulas with their appropriate
Q34: Statement: Configuration management refers largely to the
Q35: Statement: The purpose of establishing variance limits
Q36: The following chart to answer questions (a)
Q37: Statement: External project control refers to the