    Suppose a Project Was Originally Estimated to Cost $100,000, and as of a Given
Solved

Suppose a Project Was Originally Estimated to Cost $100,000, and as of a Given

Question 14

Question 14

Multiple Choice

Suppose a project was originally estimated to cost $100,000, and as of a given date the EV is $80,000 and the CPI is 0.80. What is the forecast cost to complete the project?


A) $20,000
B) $25,000
C) $24,000
D) none of these

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: How or where is work progress measured

Q10: Match the following formulas with their appropriate

Q11: Use the following information to perform an

Q12: Statement: To reduce confusion and increase the

Q13: About the project control process (circle all

Q15: Statement: By monitoring performance indexes and variances

Q16: Statement: Quality control in projects begins with

Q17: Which of the following might project managers

Q18: Statement: Project planning and project control are

Q19: Technical Performance Measurement (TPM) provides (circle all

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines