Multiple Choice
Suppose a project was originally estimated to cost $100,000, and as of a given date the EV is $80,000 and the CPI is 0.80. What is the forecast cost to complete the project?
A) $20,000
B) $25,000
C) $24,000
D) none of these
Correct Answer:

Verified
Correct Answer:
Verified