Suppose Task B Follows Task A

Question 9

Multiple Choice

Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities combined is (circle one) :


A) 3.5 months
B) 5.7 months
C) 1.6 months
D) cannot be determined