Multiple Choice
Which of the following are common techniques for pinpointing risks in projects (circle all that apply) :
A) SOW.
B) Work breakdown structure.
C) Responsibility matrix.
D) Process flowcharts.
E) Documents from prior projects.
Correct Answer: