Multiple Choice
Suppose the impact of a risk is judged to be serious, but the likelihood of it happening is judged to be very small; (circle all that apply) :
A) If the computed expected value consequence is small, the risk can be ignored.
B) The risk should be taken seriously.
C) If the computed expected value consequence is lower than others in the project, it should be addressed only if time and funds allow.
D) A different opinion should be sought that would yield a reduced or not severe impact.
Correct Answer:

Verified
Correct Answer:
Verified
Q21: Which of the following are sources of
Q22: Statement: A risk in which the expected
Q23: Statement: A project is considered risky only
Q24: Statement: In virtually all projects, both the
Q25: Statement: A risk symptom is a visible,
Q26: Match each of the following definition with
Q28: Risk checklists (circle all that apply):<br>A) List
Q29: When applying a design margin, the target
Q30: The concept of project risk is a
Q31: Risk likelihood is (circle all that apply):<br>A)