Multiple Choice
You are launching a brand new program at your company. Listed below are a set of processes that you will be performing for your program for the first time. Which of the processes will you perform first?
A) Create PWBS
B) Cost Estimating/Budgeting
C) Schedule Development
D) Resource Planning
Correct Answer:

Verified
Correct Answer:
Verified