Newton Botswani Is Managing a Program Execution When He Decides

Question 98

Multiple Choice

Newton Botswani is managing a program execution when he decides to initiate a project within the program. Which document will Newton need to authorize the project?


A) Project management plan
B) Project charter
C) Program charter
D) Authorize Projects