Multiple Choice
Which of the following is not included in the program scope management plan?
A) How to create the PWBS from the scope
B) A description of how the PWBS will be approved and managed
C) A process for how to handle requests for changes to the scope statement
D) A benefits analysis
Correct Answer:

Verified
Correct Answer:
Verified