Multiple Choice
What is the BEST way to notify the team about an approved change request?
A) Send an e-mail out to all team members
B) Walk around to communicate with each team member
C) Post on an internal website
D) Send an e-mail out to everyone in the division
E) Consult with change control process
Correct Answer:

Verified
Correct Answer:
Verified