Rick Was in the Middle of His Procurement Management Process

Question 17

Multiple Choice

Rick was in the middle of his procurement management process when he realized he was missing organizational process assets. Which is an example of an organizational process asset?


A) Project scope statement
B) Risk register
C) Current contracts
D) Lessons learned from prior projects
E) All of the above

Correct Answer:

verifed

Verified