Jill's Project Is Behind Schedule but It Needs to Be

Question 14

Multiple Choice

Jill's project is behind schedule but it needs to be delivered by a certain date. She requests additional resources to complete the project faster. Which of the following terms is this an example of?


A) Critical path
B) Crashing
C) Secondary risk
D) Float
E) Slack

Correct Answer: