Multiple Choice
Jill's project is behind schedule but it needs to be delivered by a certain date. She requests additional resources to complete the project faster. Which of the following terms is this an example of?
A) Critical path
B) Crashing
C) Secondary risk
D) Float
E) Slack
Correct Answer:

Verified
Correct Answer:
Verified