Marci is in charge of a project team. In order to meet the deadline given to her team, she establishes critical checkpoints during the process to help her determine if she is on track or off track versus her team's final deadline. What type of control is Marci utilizing?


A) Feedforward
B) Concurrent
C) Feedback
D) Loop