Solved

The Latest Finish Time for an Activity

Question 20

Multiple Choice

The latest finish time for an activity:


A) Equals the min. of LFT ? t for all immediate successors
B) Equals the max. of LFT ? t for all immediate predecessors.
C) Equals the max. of EST + t for all immediate predecessors.
D) Equals the min. of EST + t for all immediate successors.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions