The latest finish time for an activity:
A) Equals the min. of LFT ? t for all immediate successors
B) Equals the max. of LFT ? t for all immediate predecessors.
C) Equals the max. of EST + t for all immediate predecessors.
D) Equals the min. of EST + t for all immediate successors.
Correct Answer:

Verified
Correct Answer:
Verified