Which of the Following Is Not Correct About Initial Phase

Question 21

Multiple Choice

Which of the following is not correct about initial phase of a project?


A) The cost associated at the beginning of the project is highest.
B) Stakeholders have maximum influence during this phase
C) The highest uncertainty is at this stage of the project.
D) All the above statements are correct.

Correct Answer: