Which of the following is not essential requirement for contract
A) Parties must be competent
B) Should be made by free consent
C) There shall be definite and legal proposal and its acceptance.
D) Both Parties must be citizens of same country
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Contract system is suitable for big projects<br>A)Right<br>B)Wrong<br>C)none<br>D)all
Q10: Bar chart is also known as<br>A)Flow chart<br>B)Time
Q11: Bar chart is very popular because<br>A)It is
Q12: Specialized work needs departmental execution<br>A)Right<br>B)Wrong<br>C)none<br>D)all
Q13: An activity requires<br>A)Events<br>B)Time and resources<br>C)Resources<br>D)Energy
Q15: Which of the following cause of an
Q16: A drawback of bar chart is that<br>A)All
Q17: Which of the following is/are advantages of
Q18: CPM is<br>A)Event oriented<br>B)Activity oriented<br>C)Mostly event oriented<br>D)Mostly activity
Q19: Actual performance of a task is known