Actual performance of a task is known as
A) An event
B) An activity
C) A duration
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Bar chart is very popular because<br>A)It is
Q12: Specialized work needs departmental execution<br>A)Right<br>B)Wrong<br>C)none<br>D)all
Q13: An activity requires<br>A)Events<br>B)Time and resources<br>C)Resources<br>D)Energy
Q14: Which of the following is not essential
Q15: Which of the following cause of an
Q16: A drawback of bar chart is that<br>A)All
Q17: Which of the following is/are advantages of
Q18: CPM is<br>A)Event oriented<br>B)Activity oriented<br>C)Mostly event oriented<br>D)Mostly activity
Q20: The earliest method of project planning was<br>A)CPM<br>B)PERT<br>C)Bar
Q21: The construction industry has accounted for about