Danco Corporation Contracted to Construct a Construction Crane Over the Current

Question 1

Essay

Danco Corporation contracted to construct a construction crane over the current and the next two years. The contract price is $2,000,000 and construction costs are estimated at $1,600,000. Determine Danco's income in this and the next two years given the following information:
Year 1: actual costs = $250,000
Year 2: actual costs = $975,000
Year 3: actual costs = $425,000
a. under the percentage-of-completion method.
b. under the completed contract method.