Multiple Choice
Who is responsible for determining the Change Authority and change budget?
A) Corporate or Programme Management
B) Project Manager
C) Project Board
D) Executive
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q36: Which of the following activities does PRINCE2
Q37: A member of the Project Board should:<br>1)Be
Q38: A Risk Cause is which of the
Q39: Which of the following products is NOT
Q40: In which of the following reports are
Q42: At what point is a Stage Plan
Q43: Which documents are used to produce the
Q44: Product Descriptions are contained within which other
Q45: Who can order the closure of a
Q46: Which of the following risk responses involves