Which of the following activities does PRINCE2 recommend when preparing the Communication Management Strategy?
1) Review the project brief
2) Review the risk and issue registers
3) Consult with the suppliers that will be used throughout the project
4) Consult with project assurance
A) 1, 2
B) 3, 4
C) 1, 2, 4
D) 2, 3, 4
Correct Answer:

Verified
Correct Answer: