Which of the following should always be taken into account when defining the number and length of stages?
1) The project budget
2) Where the key decision points need to be
3) The amount of risk
4) The confidence levels of the Project Manager and Project Board


A) 1, 2, 3, 4
B) 1, 2, 3
C) 2, 3, 4
D) 1, 2, 4

Correct Answer: