Multiple Choice
Is it possible for the members of the Project Board to provide guidance to the Project Manager outside the standard documentation/reporting procedures specified in PRINCE2?
A) No. Communication from the Project Board must always occur at predefined points.
B) Yes, but only in response to a PRINCE2 report from the Project Manager.
C) Yes, but only if the Project Manager specifically requests guidance.
D) Yes. They are allowed to give ad-hoc direction any time they like.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: During which Process is the Work Package
Q11: A Change Authority is responsible for:<br>A)Reviewing and
Q12: Which document defines the acceptance criteria and
Q13: Which of the following should always be
Q14: Which roles must be independent of each
Q16: When a project is closed, all project
Q17: Which of the following are fields in
Q18: In the Quality Audit Trail, Quality Control
Q19: As part of which process are decisions
Q20: The principle of Learning from Experience dictates