    Who Is Responsible for Confirming Programme Closure
Solved

Who Is Responsible for Confirming Programme Closure

Question 72

Question 72

Multiple Choice

Who is responsible for confirming programme closure?


A) Senior Responsible Owner
B) Programme Manager
C) Business Change Manager
D) Programme Office

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q67: One of these statements is false. Which

Q68: Which of the following is NOT an

Q69: Which of these is NOT one of

Q70: How does MSP define Programme Management?<br>A)The management

Q71: Which of the following documents details the

Q73: Which of the following is NOT one

Q74: Which answer identifies two of the principles

Q75: For which of the following is the

Q76: Which of the following would you find

Q77: During the development of which document would

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines