Multiple Choice
For which of the following is the Business Change Manager responsible?
A) Managing communications with the Programme Board
B) Advising and supporting the SRO
C) Managing the programme's budget
D) Ensuring business ownership of Benefit Profiles
Correct Answer:

Verified
Correct Answer:
Verified