Multiple Choice
Part of the project output to the strategic objective chain is in which order?
A) End Benefit -> Outcome -> Business Change
B) Business Change -> End Benefit -> Outcome
C) Business Change -> Outcome -> Intermediate Benefit
D) Outcome -> Business Change -> Intermediate Benefit