Multiple Choice
Which of these is NOT part of the core information in a Programme Plan?
A) Risk and assumptions
B) Schedule showing the programme's tranches
C) Schedule of communications activities, including target audiences for each
D) Transition plans
Correct Answer:

Verified
Correct Answer:
Verified