Multiple Choice
Which of these is a main reason for closing a programme?
A) The changes the programme was created to bring about have been delivered.
B) The Programme Office has completed the Configuration Management process.
C) The Business Change Manager has confirmed that all transitions have taken place.
D) All the programme risks have been resolved.