Multiple Choice
Which document is "used to control and track the progress and delivery of the programme and resulting outcomes"?
A) Programme Plan
B) Programme Preparation Plan
C) Monitoring and Control Strategy
D) Programme Brief
Correct Answer:

Verified
Correct Answer:
Verified