Question 22

Multiple Choice

Lean cost and productivity measurements may include employee labor productivity and individual or group sales productivity. Calculate the number of products produced per hour by a factory that produced 16,000 items with 8 employees working 8-hour shifts 5 days per week, with a total of 40 hours each per week, for 4 weeks.


A) 16 products per hour
B) 12.5 products per hour
C) 42 products per hour
D) 7 products per hour