A Project Manager Has Multiple Lean Projects She Manages Concurrently

Question 117

Multiple Choice

A project manager has multiple lean projects she manages concurrently. Why would she employ a corrective action system?


A) To ensure implementation and establish that timelines are followed and sustainment is enacted.
B) To ensure team members complete assigned team tasks.
C) To ensure documentation for compliance purposes.
D) To eliminate sustainment activities.

Correct Answer: