In Hinson v. N&W Construction, where Hinson submitted the low bid to N&W for plumbing work to be part of a larger construction project by N&W, but then refused to do the work when construction was started by N&W, the court held that Hinson's bid:
A) could not be relied upon by N&W because he was not licensed for such work
B) was unrealistically low, which N&W recognized, so it could not rely on the bid
C) was valid, so there was a breach of contract; Hinson was liable for the full value of the contract
D) was valid, so there was a breach of contract, so he was liable for the extra costs incurred by N&W
E) none of the other choices
Correct Answer:

Verified
Correct Answer:
Verified
Q478: In Hinson v. N&W Construction, where Hinson
Q479: Withdrawal of an offer by the offeror
Q480: Most contracts are unilateral.
Q481: In Scheerer v. Fisher, where Scheerer claimed
Q482: A binding promise is:<br>A) a contract by
Q484: For Amy's sixteenth birthday her parents give
Q485: Quasi contract is used to prevent quantum
Q486: You leave your poodle at a new
Q487: Which of the following is a type
Q488: A counteroffer terminates the original offer.