Multiple Choice
During the implementation phase of the systems development life cycle (SDLC) ,in _____ conversion,the old and new systems run simultaneously for a short time to ensure the new system works correctly.
A) parallel
B) phased-in-phased-out
C) plunge
D) pilot
Correct Answer:

Verified
Correct Answer:
Verified