Multiple Choice
During the implementation phase of the systems development life cycle (SDLC) ,in _____ conversion,as each module of a new system is converted,the corresponding part of an old system is retired.
A) parallel
B) phased-in-phased-out
C) plunge
D) pilot
Correct Answer:

Verified
Correct Answer:
Verified