Solved

Ivy Inc Has Planned a Simple Project Having Four Tasks

Question 18

Multiple Choice

Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true? A) None of the tasks have slack. B) Task O has 3 days of slack. C) Task L has 4 days of slack. D) Task D has 2 days of slack. E) Task L has 3 days of slack.
-Based on the information, which of the following statements is true?


A) None of the tasks have slack.
B) Task O has 3 days of slack.
C) Task L has 4 days of slack.
D) Task D has 2 days of slack.
E) Task L has 3 days of slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions