Poisson Corporation Has the Following Six Tasks and the Associated

Question 21

Multiple Choice

Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has non-zero slack? A) S B) O C) E D) F E) N
-Which task has non-zero slack?


A) S
B) O
C) E
D) F
E) N