Multiple Choice
Assume that all of the jobs below arrived at the same time. Also assume that transfer times are zero and jobs cannot be split
-Using a Gantt chart and the processing order as per the critical ratio (CR) rule, determine the average lateness.
A) -0.4 hrs
B) 6.6 hs
C) 11.6 hrs
D) 15 hrs
E) 18 hrs
Correct Answer: