A tier-two supplier needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table.
-The process engineers design a line that contains 5 stations. What is the efficiency?
A) 52.73%
B) 60.27%
C) 70.31%
D) 84.38%
E) Need more information to answer the question